Update Plot

 

The user can draw plot curves with a name already exist in a chart for other rplt files. It is useful if the user wants to see a new plot curve compared with a previous plot curve.

 

Step to use

1.  Analyzes a model. (The user has to check on Create Output Folder option in the Simulation dialog in the Model Setting group of the Home tab.)

2.  Draws plot curves on the Plot Windows.

 

Figure 1  Draw plot curves

 

3.  Analyzes the model by changing the parameters.

4.  Returns to Plot Window and then imports the last rplt file.

 

Figure 2  Import Last Simulated Rplt File icon of the Import group in the Home tab

 

5.  Clicks the Update Plot icon.

 

Figure 3  Update Plot icon of the Draw group in the Home tab

 

6.  Checks the data to be updated.

 

Figure 4  Update Plot dialog box

 

Figure 5  After performing the Update Plot function

 

Note

This function is activated when the rplt file should be more than 2 and a plot curve should be drawn at least one.